EXAMPLE TIMELINE
When we propose to do it:
Contract proposal submitted January 6 Contract acceptance January 27 Final design acceptance February 3 Site prep complete March 24 Components delivery to site March 31 Exhibit install complete May 1 Animal introduction to exhibit May 15 Soft open to public May 20 Open to public Memorial Day Weekend Exhibit closes to public Labor Day Weekend Exhibit breakdown and removal End of September